Changes commencing July 16th, 2025
Comparing the consolidation as at June 20th, 2025 with July 16th, 2025 · 76 changes
— Not present in the earlier version —
A wall constructed within 900mm of a lot boundary must be built in accordance with the support method proposed by the professional engineer’s report provided with the application for the complying development certificate. cl 3BA.10: Ins 2025 (355), Sch 1[6].
Based on content from the New South Wales Legislation website sourced at 2025-07-16. For the latest information on New South Wales Government legislation please go to https://www.legislation.nsw.gov.au.