Changes commencing July 16th, 2025
Comparing the consolidation as at June 20th, 2025 with July 16th, 2025 · 76 changes
— Not present in the earlier version —
(3) Despite subclauses (1) and (2), the excavation must not exceed a maximum depth, measured from ground level (existing), of 1m if— (a) the land is identified as Class 3 or 4 on an Acid Sulfate Soils Map, or (b) the land is within 40m of a waterbody (natural), or (c) the excavation is an aquifer interference activity within the meaning of the Water Management Act 2000 .
Based on content from the New South Wales Legislation website sourced at 2025-07-16. For the latest information on New South Wales Government legislation please go to https://www.legislation.nsw.gov.au.