Changes commencing July 16th, 2025
Comparing the consolidation as at July 11th, 2025 with July 16th, 2025 · 21 changes
— Not present in the earlier version —
(3A) Despite subsection (3), for development specified in State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 , Part 3BA, a certifier must not issue a complying development certificate until at least 7 days after the certifier has given written notice to— (a) if the development will be on land in a residential zone—each neighbour on land in a residential zone, and (b) if the certifier is not the council for the area in which the development will be carried out—the council.
Based on content from the New South Wales Legislation website sourced at 2025-07-16. For the latest information on New South Wales Government legislation please go to https://www.legislation.nsw.gov.au.